Fees and charges
The last fee review of the permit scheme was carried out to cover the period 2021 to 2024 (Years 10 to 12 of the permit cycle). The permit fees have now been increased to the maximum level currently allowed by the Department For Transport (DFT).
Road catagory 0, 1, and 2 and traffic 3 and 4 designated traffic sensitive
Fee levels per permit or Provisional Advance Authorisation |
||
---|---|---|
Road catagory 0, 1, and 2 and traffic 3 and 4 designated traffic sensitive | ||
Rotherham Council Permit Fee | Maximum allowable fee (Department for Transport) | |
Provisional advance authorisation |
£105 |
£105 |
Major activity permit (1 to 3 days duration) |
£65 |
£65 |
Major activity permit (4 to 10 days duration) |
£130 |
£130 |
Major activity permit (11 days or more duration) and all major activities requiring a traffic regulation order |
£240 |
£240 |
Standard activity permit |
£130 |
£130 |
Minor activity permit |
£65 |
£65 |
Immediate activity permit |
£60 |
£60 |
Road catagory 3 and 4 designated non traffic sensitive
Fee levels per permit or Provisional Advance Authorisation |
|||
---|---|---|---|
Road catagory 3 and 4 designated non traffic sensitive | |||
Rotherham Council Permit Fee | Rotherham Council Permit Fee (Proposed) | Maximum allowable fee (Department for Transport) | |
Provisional advance authorisation |
£73 |
£75* |
£75 |
Major activity permit (1 to 3 days duration) |
£45 |
£45 |
£45 |
Major activity permit (4 to 10 days duration) |
£75 |
£75 |
£75 |
Major activity permit (11 days or more duration) and all major activities requiring a traffic regulation order |
£136 |
£150* |
£150 |
Standard activity permit |
£75 |
£75 |
£75 |
Minor activity permit |
£45 |
£45 |
£45 |
Immediate activity permit |
£40 |
£40 |
£60 |
* Change only applies to PAA applications, and applications for a major permit of more than 10 days in duration
Permit variation fee
£45 for activities on catagory 0, 1, and 2 and traffic 3 and 4 designated traffic sensitive.
£35 for activities on category 3 and 4 non traffic sensitive streets.
If a permit variation moves an activity into a higher fee category, the Promoter will be required to pay the difference in permit fee as well as the permit variation.